project to expand the broadband network across the country is in the final stages

The project to expand the broadband network across the country has reached the stage of completion. According to the Nepal Telecommunication Authority, the project has been completed in Phagun out of the target of providing internet to 706 localities under the project.

Now only 34 ward offices have internet connection left. According to NEA, 5,899 ward offices have been connected to the internet so far.

There is a facility to use the internet for free for two years in all the designated places including the office connected in this way. According to NEA, internet connection has been completed in all the health institutions and secondary schools under the designated local level.

According to NEA, the project aims to connect 4,237 health institutions and 5,299 secondary schools with internet connection. According to NEA, the work of internet connection has been completed 99.79 percent by the end of the project.

NEA had allocated Rs. 5.67 billion from the Rural Telecommunication Development Fund for this project. So far, Rs. 4.47 billion or 78.81 percent of the total allocation has been spent.

Under the project, NEA was tasked to lay optical fiber in designated public bodies through licensed telecommunication service providers.

NEA had implemented the project in 74 districts by dividing it into 18 packages. For this, the responsibility of fiber network expansion was assigned by competing different service providers in different packages.

Although the project was initially targeted to be completed within two years, it has been completed after about six years. According to the package, two years of free internet access has expired in some places.

NEA has paved the way for providing services in such places by charging internet fee applicable in Kathmandu Valley.

According to NEA, evaluation and verification of eight packages has been completed so far.

Similarly, the evaluation and certification work of the first phase has been completed by the consultant of one project and the report of evaluation and certification work of the second phase of three projects has been received.

Similarly, under the third phase of the two projects, a mandate has been issued to the consultant for evaluation and verification, according to NEA.

Accelerating information highway

The information highway, which has not been able to move forward even after the agreement has been signed for a long time, is slowly gaining momentum. According to NEA, 56.45 percent progress has been achieved under the first package of the project to extend optical fiber to all district headquarters and municipalities based on the Mid-Hill Highway.

According to the NEA’s data up to Fagun, 1,230 kilometers of optical fiber has been laid so far in State 1, Madhesh State and Bagmati State under Package One. The package aims to lay 2,179 kilometers of optical fiber. Nepal Telecom has been doing its work.

In Gandaki and Lumbini provinces under Package-2, the work of information highway has not started yet. NEA had decided not to extend the contract to United Telecom (UTL), which was entrusted with the package-2 after the work did not start on time.

However, UTL had filed a case in the Supreme Court against the decision and an interim order was issued not to extend the agreement until the case was settled.

The work of laying optical fiber has already started in Karnali and Far Western Provinces under Package-3. Under this package entrusted to Nepal Telecom, the work of laying 12.04 or 240 kilometers of optical fiber has been completed. One thousand 992 kilometers of optical fiber will have to be laid under this package.

NEA has allocated Rs 9.89 billion for the information highway out of which Rs 615.5 million has been paid in package 1 so far and Rs 400 million has been paid in advance under package 2. The information highway will provide the necessary infrastructure for high speed internet flow.

you may also like to read about: Lal Bahadur Rajwar, Danda Singh, Santa Bahadur, and listen to popular Hindi music of the best singers, and watch movies based on love stories do you also want to play games on iOS,  after you get tired and sleepy you can listen and watch to the healing mediation music for deep sleep and relaxation videos in Rajawar mediation music and videos of chicks, hen, dog, and chicken friendship. after visiting natural places on the screen you can take pictures and reduce their size by using the Image Compressor tool the best tool available online to compress images, age calculator, English to Nepali, generate fancy text or fancy text generator to make your text look unique can attract your friends. love calculator you can capture the image file and convert them from PNG to JPEG converter online and also image to webp for the smaller size. to share these pictures online you have to use WhatsApp messaging service by downloading WhatsApp software. you can use typing master online to speed up your typing skills. you can convert unit from the unit converter. you can also download youtube thumbnails from a youtube thumbnail downloader. you can look at the Nepali calendar for celebration or festival dates. you can also recover your old photos and videos through CD DVD Recovery Toolbox Software for free and you can share them by posting them to your blogs and websites hosted on the best web hosting platforms or service providers in the world.

The project to expand the broadband network across the country has reached the stage of completion. According to the Nepal Telecommunication Authority, the project has been completed in Phagun out of the target of providing internet to 706 localities under the project.

Now only 34 ward offices have internet connection left. According to NEA, 5,899 ward offices have been connected to the internet so far.

There is a facility to use the internet for free for two years in all the designated places including the office connected in this way. According to NEA, internet connection has been completed in all the health institutions and secondary schools under the designated local level.

According to NEA, the project aims to connect 4,237 health institutions and 5,299 secondary schools with internet connection. According to NEA, the work of internet connection has been completed 99.79 percent by the end of the project.

NEA had allocated Rs. 5.67 billion from the Rural Telecommunication Development Fund for this project. So far, Rs. 4.47 billion or 78.81 percent of the total allocation has been spent.

Under the project, NEA was tasked to lay optical fiber in designated public bodies through licensed telecommunication service providers.

NEA had implemented the project in 74 districts by dividing it into 18 packages. For this, the responsibility of fiber network expansion was assigned by competing different service providers in different packages.

Although the project was initially targeted to be completed within two years, it has been completed after about six years. According to the package, two years of free internet access has expired in some places.

NEA has paved the way for providing services in such places by charging internet fee applicable in Kathmandu Valley.

According to NEA, evaluation and verification of eight packages has been completed so far.

Similarly, the evaluation and certification work of the first phase has been completed by the consultant of one project and the report of evaluation and certification work of the second phase of three projects has been received.

Similarly, under the third phase of the two projects, a mandate has been issued to the consultant for evaluation and verification, according to NEA.

Accelerating information highway

The information highway, which has not been able to move forward even after the agreement has been signed for a long time, is slowly gaining momentum. According to NEA, 56.45 percent progress has been achieved under the first package of the project to extend optical fiber to all district headquarters and municipalities based on the Mid-Hill Highway.

According to the NEA’s data up to Fagun, 1,230 kilometers of optical fiber has been laid so far in State 1, Madhesh State and Bagmati State under Package One. The package aims to lay 2,179 kilometers of optical fiber. Nepal Telecom has been doing its work.

In Gandaki and Lumbini provinces under Package-2, the work of information highway has not started yet. NEA had decided not to extend the contract to United Telecom (UTL), which was entrusted with the package-2 after the work did not start on time.

However, UTL had filed a case in the Supreme Court against the decision and an interim order was issued not to extend the agreement until the case was settled.

The work of laying optical fiber has already started in Karnali and Far Western Provinces under Package-3. Under this package entrusted to Nepal Telecom, the work of laying 12.04 or 240 kilometers of optical fiber has been completed. One thousand 992 kilometers of optical fiber will have to be laid under this package.

NEA has allocated Rs 9.89 billion for the information highway out of which Rs 615.5 million has been paid in package 1 so far and Rs 400 million has been paid in advance under package 2. The information highway will provide the necessary infrastructure for high speed internet flow.

you may also like to read about: Lal Bahadur Rajwar, Danda Singh, Santa Bahadur, and listen to popular Hindi music of the best singers, and watch movies based on love stories do you also want to play games on iOS,  after you get tired and sleepy you can listen and watch to the healing mediation music for deep sleep and relaxation videos in Rajawar mediation music and videos of chicks, hen, dog, and chicken friendship. after visiting natural places on the screen you can take pictures and reduce their size by using the Image Compressor tool the best tool available online to compress images, age calculator, English to Nepali, generate fancy text or fancy text generator to make your text look unique can attract your friends. love calculator you can capture the image file and convert them from PNG to JPEG converter online and also image to webp for the smaller size. to share these pictures online you have to use WhatsApp messaging service by downloading WhatsApp software. you can use typing master online to speed up your typing skills. you can convert unit from the unit converter. you can also download youtube thumbnails from a youtube thumbnail downloader. you can look at the Nepali calendar for celebration or festival dates. you can also recover your old photos and videos through CD DVD Recovery Toolbox Software for free and you can share them by posting them to your blogs and websites hosted on the best web hosting platforms or service providers in the world.

More from author

Related posts

Advertismentspot_img

Latest posts

Infodevelopers ICT Awards 2022 concluded with enthusiastic participation, distribution of awards in 14 categories

The grand finale of the ICITY Award, which is known as the prestigious award in the field of information and communication technology organized by...

Realme C33 phone with 50MP AI camera launched in Nepali market

Smartphone brand Realme has unveiled a new version of Realme C33, a stylish budget C-series with the highest pixels in the entry-level segment with...

Xiaomi Nepal is expanding its portfolio in smart TV and ecosystem, what is the price?

Xiaomi Nepal has announced the lineup of smart TVs along with Xiaomi Smart Air Fryer. The smart TV lineup includes Redmi Smart TV 43...

Want to stay up to date with the latest news?

We would love to hear from you! Please fill in your details and we will stay in touch. It's that simple!